Monday, October 10, 2011

Second Week of Construction

Site work ongoing

Rebar cages for the caissons are beginning
Overall site view from the parking garage. Two crawler cranes were delivered this week
Site work ongoing
Material used for Caisson drilling

Construction Begins 9/22

Equipment was brought to the site the week of September 21st, including a quadruple wide trailer


The commuter lot was closed to student parking on 9/21/11


During the first week, workers installed silt fencing, site fencing, and utility markings